Ottawa Marriott

  • Client: Dynamic
  • Duration: 2024-Present
  • Value: CAD $600K

Scope of work: Run new data cables through existing conduit infrastructure and patch over existing cable to new Data rack (Supplied and installed by ACE). install CCTV cameras/ Security system. install and program access points. Provide TV procurement and installation. (project handover expected 2025)

Staybridge Toronto

  • Client: Regal investments
  • Duration: 2024-Present
  • Value: CAD $1M

Scope of work: Run new data, AV cables through new conduit infrastructure and patch all cable to new Data rack (Supplied and installed by ACE). Install CCTV cameras/ Security, intrusion, intercom systems. install and program access points. Install cabling infrastructure for 100 parking spots of metering EV chargers. Install Door operators RFID card readers and door hardware. Install parking garage door. Certify/test and label all cables and at termination points.(Project handover expected June 2025)

Fairfield Marriott Bolton

  • Client: Dynamic
  • Duration: 2025-Present
  • Value: CAD $700K

Scope of work: Run new data, AV cables through new conduit infrastructure and patch all cable to new Data rack (Supplied and installed by ACE). Install CCTV cameras/ Security, intrusion, intercom systems. install and program access points. Install cabling infrastructure Install Door operators RFID card readers and door hardware. Install parking garage door. Certify/test and label all cables and at termination points. Install and supply telephone system (project handover expected 2026).

Napanee Tru by Hilton

  • Client: Dynamic
  • Duration: 2024- present
  • Value: CAD $400k

Scope of work: Physically installing Data cable infrastructure conduits and termination on new IT racks supplied and installed by ACE. CCTV cameras, access points programed and installation. tv procurement and installation. Handover of cabling documentation and certification (Estimated to be turned over by end of 2025).

Kincardine Staybridge

  • Client: Track One Project Management INC
  • Duration:2024-Present
  • Value: CAD $300k

Scope of work: Physically installing Data cable infrastructure conduits and termination on new IT racks (supplied and installed by ACE). CCTV cameras, access points programed and installed. Handover of cabling documentation and certification (Estimated turnover by end of 2025).

Hyatt Place Toronto International Airport

  • Client: MAGA
  • Duration: 2024-Present
  • Value: CAD $400K

Scope of work: Voice/Data cabling install, test and certify, CCTV cameras installation, audio visual installation, and board room integration.